Victoria Square Construction Update Q1 2022

PUBLICATION: GROWLAND
DATE:

AWARD WINNING DEVELOPMENT

With its extensive public realm and bold architecture, Victoria Square has secured the rare honour of being named the finalist in the highly acclaimed UDIA Awards For Excellence.

CONSTRUCTION UPDATE

As we move into summer, construction activity continues site a Victoria Square with builders busy to make sure your homes will be delivered on time and to the highest degree of quality. Following is an update on recent construction progress at VIC SQ Stage 2 (VS. O3 & VS. O4). 

  • Perimeter shotcrete walls completed.
  • Bulk Excavation works completed.
  • Detailed excavation of pad footing underway.
  • VS. O3 & VS. O4 tower raft slabs poured.
  • VS. O3 tower jump form system installed.
  • VS. O4 tower jump form system installation underway.
  • VS. O3 core walls poured up to G level.
  • VS. O4 core walls poured up to LG2 level.

We are on track for completion of these two towers in Mid-2023.